Feasibility Study of Performance Low Capacity Hybrid Energy Power Plant System in Remote Area

Samsurizal Samsurizal, Hastuti Azis, Septiannissa Azzahra, Wahyuni Martiningsih

Abstract


The fossil energy utilization for electricity
generation is currently starting to be limited because it is predicted
that the availability of fossil energy for the next few decades will
run out. Renewable energy is an alternative energy that can be
used to generate electricity. Solar power plant is one of the
electrical energy generators with renewable energy sources that
have been widely used. Solar power plant is a Distributed
Generator that can be applied directly to consumers and it is very
suitable for use in remote areas which currently still use diesel as
a fuel for power generation. In this research, the design of a hybrid
power generation system between Soalr Energy and Wind will be
carried out to replace the use of diesel as a source of electricity
generation. After the generator design is done, then the
performance test of the hybrid system will be carried out in order
to see the feasibility of the design that has been made. From the
test results, the results of the Hybrid Energy Generator have
efficiencies ranging from 10-12% where this shows that the power
plant system is still said to be unable to work efficiently. The
average amount of energy produced from this Hybrid PLT system
is 1,304 kWh per day. Based on the results of the economic
feasibility analysis, that the use of the hybrid system is able to
produce savings of Rp. 1,700 – Rp. 2,100/kWh per day


Keywords


hybrid, Energy Generation, testing, performance

Full Text:

PDF

References


Avianti Fontana, Zainal Arifin, (2015) PLN Research Institute, Jakarta.

Dahliya, D., Samsurizal, S., & Pasra, N. (2021). Efisiensi Panel Surya Kapasitas 100 Wp Akibat Pengaruh Suhu Dan Kecepatan Angin. SUTET, 11(2), 71-80

F. Lasnier and T.G. Ang, (1990), “Photovoltaic Sistem Handbook”, Adam Hilger, Bristol, and New York.

https://web.pln.co.id/media/siaran-pers/2021/01/tarif-listrik-triwulan-1-2021-tidak-naik. 2021

https://www.esdm.go.id/id/media-center/arsip-berita/tarif-tenaga-listrik-pelanggan-non-subsidi-periode-april-juni-2021-tetap. 2021

Irawati, Rina. Zuhaidi. (2012). “Analisa Pembangkit Listrik Tenaga Hibrida Untuk Pemenuhan Kebutuhan Energi Listrik Di Pulau Pramuka”. Ketenagalistrikan dan Energi Terbarukan Vol. 11 No.2, Desember.

Pusat Penelitian dan Pengembangan Teknologi Ketenagalistrikan, Energi Baru, Terbarukan, dan Konservasi Energi (esdm.go.id). Januari 2021.

Putranto, Adityo dkk. (2011). “Rancang Bangun Turbin Angin Vertika Untuk Penerangan Rumah Tangga”. Fakultas Teknik Universitas Diponegoro.

Rencana Umum Penyediaan Tenaga Listrik Tahun 2019-2028. PT. PLN (Persero)

Surahman, Edy. Ismail Nahkoda, Yusuf. (2019). “Rancang Bangun Pembangkit Listrik Tenaga Hybrid Photovoltaic dan Turbin Angin Sumbu Vertikal Menggunakan Generator Magnet Permanen Fluks Aksial Tiga Fasa Putaran Rendah”. Jurnal Skripsi Elektro S1 ITN Malang.

Susanto, Alex. Abdul Azis, Malik. 2015. “Pembangkit Listrik Tenaga Angin”. Fakultas Teknik Unnes.

Siregar, M. A. R., Sunanda, W., & Putra, G. B. (2019). Planning Of Photovoltaic And Pln Hybrid Sistem In Bangka Belitung University. Jurnal Ecotipe (Electronic, Control, Telecommunication, Information, and Power Engineering), 6(2), 56-60.

Pansuri, M. I. (2019). Perencanaan Sistem Pembangkit Listrik Hybrid Tenaga Surya (PLTS) dan diesel generator di Pulau Kelapan Kabupaten Bangka Selatan (Doctoral dissertation, Universitas Bangka Belitung).

Custer, J., & Lianda, J. (2018). Rancang Bangun Pembangkit Listrik Hybrid Angin Dan Surya di Pulau Bengkalis. Jurnal PROtek Vol, 5(2).

Chamdareno, P. G., & Hilal, H. (2018). Analisa Pembangkit Listrik Tenaga Hybrid PLTD-PLTS di Pulau Tunda Serang Banten. RESISTOR (elektRonika kEndali telekomunikaSI tenaga liSTrik kOmputeR), 1(1), 35-42.




DOI: http://dx.doi.org/10.32497/eksergi.v18i2.3539

Refbacks

  • There are currently no refbacks.


Mechanical Engineering Department
Politeknik Negeri Semarang
Jl. Prof. Sudarto, SH., Tembalang, Semarang
Phone (024) 7478384; Fax: (024) 7472396;

Email: jurnal.eksergi@polines.ac.id

Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

View Statistics View MyStat