ANALISIS PENJADWALAN DAN ALOKASI SUMBER DAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN MICROSOFT PROJECT (Studi Kasus Pekerjaan Struktur Proyek XYZ)
DOI:
https://doi.org/10.32497/wahanats.v26i1.2647Keywords:
construction, project management, microsoft project, resourcesAbstract
One of the computer applications that can be used in project management control is the Microsoft Project application. With Microsoft Project , information related to activities that fall into the critical trajectory and allocation of resource placement can be known, so that the project does not experience delays and a decrease in work productivity. Based on the results of the analysis using the Microsoft project, it is found that activities are included in the critical trajectory, namely: pile work, soldier pile, excavation, excavation fireplace, brickwork installation, work floor, pile cap and superstructure work. The results of the analysis show the need for the number of workers from the 1st month to the 8th month: 31, 43, 43, 40, 37, 31, 10. The needs of the foreman are: 2, 3, 3, 2, 2, 2 , 2, 1. For crane operator resources in the 1st month and 2nd month is as many as 3 people. Subcontractor 1 and subcontractor 2 require as many as 1 person in the resources of the 2nd month to the 3rd month. A mason is needed from the 2nd to the 8th month: 12, 9, 8, 7, 7, 6, 2. Resource analysis for the head mason every month: 3, 3, 2, 2, 2, 2, 1. Analysis of the allocation of resource placement can be carried out in several stages if a graph of the resources fluctuates or does not comply with the principle of resource allocation.References
Ervianto, W. I., 2005, Manajemen Proyek Konstruksi, Yogyakarta: Andi
Husen, A., 2010, Manajemen Proyek Perencanaan, Penjadwalan & Pengendalian Proyek, Yogyakarta: Andi
Hutagaol, J.D., 2013, Perbandingan Metode Critical Path Method (CPM), Precedence Diagram Methode (PDM) & Line of Balance (LOB) terhadap Proyek Repetitif, Jurusan Teknik Sipil, Universitas Diponegoro, Semarang
Ladda, Shubam, Prerna Chanda and Sneha Khedekar., 2017, Planning and Scheduling of a Project Using Microsoft Project, International Journal of Advanced Research, AISSMS COE, Pune, India
Chaudhury, A.R., S.K. Nagaraju, B. Sivakonda Reddy, 2012, Resource Management In Construction Projects ”“ A Case Study, International Journal (ESTIJ), IRACST ”“ Engineering Science and Technology, 2012
Laksito, B., 2005, Studi Komparatif Penjadwalan Proyek Konstruksi Repetitif menggunakan Metode Penjadwalan Berulang (RSM) & Metode Diagram Preseden (PDM), Media Teknik Sipil, Universitas Sebelas Maret, Surakarta
Luthan, P.L.A & Syafriandi, 2017, Manajemen Konstruksi dengan Aplikasi Microsoft Project, Yogyakarta: Andi
Sharanyasreenivas, J., G. Gajalakshmi, K. Ravi Theja, 2017, Project Planning, Scheduling and Preparation of Quality Assurance Control Documents, International Research Journal of Engineering and Technology (IRJET), Structural Engineering & Construction Management, GVIC, Madanapalle, A.P., India
Analisa Harga Satuan Pekerjaan (AHSP) Bidang Pekerjaan Umum, Kementerian Pekerjaan Umum, Jakarta, 2012
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).