KAJIAN PERBANDINGAN PENGARUH PENGGUNAAN DINDING PRECAST DENGAN DINDING KONVENSIONAL PADA PROYEK CORDOVA SEMARANG
Abstract
Innovation in the world of construction is something that is indispensable, one of the
innovations in the construction sector is precast. The use of precast is expected to be
able to reduce project costs to accelerate the duration of work. But in fact, the
products of innovation in the world of construction have not been fully able to have
a positive impact, both in terms of cost, quality, time, waste, on project development.
Products of innovation are usually not necessarily in accordance with the wishes
and needs of the customer. The purpose of this research is to analyze the
comparison of products in terms of time, cost, quality, waste, and in terms of K3L
between projects using precast walls and projects using the lightweight brick wall
method. This research was conducted by (1) conducting a project simulation if the
project did not use precast, (2) comparing a real project with a simulation project in
terms of cost, quality, time, waste, and K3L. The use of precast in the Cordova
project when compared to a simulation project that uses lightweight bricks results in
(1) in terms of time saving 36,84 % on the simulation results project (2) in terms of
costs can be reduced by Rp. 101.488.543,99 (3) in terms of quality precast material
has The quality is better than the lightweight bricks (4) in terms of waste, in the
simulation result project it creates more waste (5) in terms of K3L, the use of
precast is more environmentally friendly than the simulation results project.
Keywords
Full Text:
PDFReferences
Abduh, M., 2007, Inovasi Teknologi
dan Sistem Beton Pracetak di
Indonesa: Sebuah Analisa
Rantai Nilai, Seminar dan
Pameran HAKI 2007.
Adi, RY., Nurhuda, I., 2014,
Perilaku dan Kekuatan
Sambungan Kolom pada
Sistem Beton Pracetak.
Jurusan Teknik Sipil Fakultas
Teknik Universitas
Diponegoro, Semarang
Handayani, S., 2010, Kualitas Batu
Bata Merah Dengan
Penambahan Serbuk Gergaji,
Jurusan Teknik Sipil Fakultas
Teknik Universitas Negeri
Semarang, Semarang
Husen, A., 2009, Manajemen Proyek
Edisi Revisi Diterbitkan oleh
Penerbit CV ANDI
Yogyakarta.
Nurdiana, A., 2015, Analisis Biaya
Tidak Langsung Pada Proyek
Pembangunan Best Western
Star Hotel & Star Apartement
Semarang. Jurusan Teknik
Sipil Fakultas Teknik
Universitas Diponegoro,
Semarang.
Purwaningsih, I., 2014,
Perbandingan Biaya dan
Waktu Pada Pelaksanaan
Pekerjaan Konstruksi dengan
Beton Konvensional dan Fly Slab. Jurusan Teknik Sipil
Fakultas Teknik Universitas
Diponegoro, Semarang.
Sahid, MN., dan Safi’I, 2010,
Analisa Perbandingan
Produktivitas Kerja Pada
Pekerjaan Dinding Bata
Konvensional Dengan
Material Limbah Serat Alami
Terhadap Sifat Fisika Bata
Merah Skripsi FMIPA
Universitas Negeri Padang,
Sumatera Barat.
Soeharto, I., 1995, Manajemen
Proyek (Dari Konseptual
Sampai Operasional), Jakarta
: Erlangga.
Soeharto, I., 1999, Manajemen
Proyek (Dari Konseptual
Sampai Operasional), Jakarta:
Erlangga.
Tata Cara Perencanaan Beton
Pracetak dan Beton Prategang
untuk Bangunan Gedung
(SNI 7833, 2012).
Utomo, PP., 2017, Analisis
Perbandingan Biaya dan
Waktu Pelaksanaan Pekerjaan
Dinding Eksterior
Menggunakan Dinding Beton
Pracetak dan Dinding Panel
Beton Ringan pada Proyek
Apartemen Gunawangsa
Merr Surabaya. Jurusan
Teknik Sipil Fakultas Teknik
Sipil dan Perencanaan Institut
Teknologi Sepuluh
Nopember, Surabaya.
Wahyudi, H., dan Hanggoro, HD.,
, Laporan Tugas Akhir:
Perencanaan Struktur
Gedung BPS Provinsi Jawa
Tengah Menggunakan
Beton Pracetak. Jurusan
Teknik Sipil Fakultas Teknik
Universitas Diponegoro,
Semarang.
Wohon, Fransisko Yeremia, 2015,
Analisa Pengaruh Percepatan
Durasi Pada Biaya Proyek
Menggunakan Program
Microsoft Project 2013 (Studi
Kasus : Pembangunan Gereja
GMIM Syaloom
Karombasan). Jurusan Teknik
Sipil Fakultas Teknik
Universitas Sam Ratulangi,
Manado
Womack, J.P. and Jones, D.T., 2003,
Lean Thinking: Banish waste
and create wealth in in your
corporation, revised and
updated, Free Press.
Yudakusumah, T., 2012, Aplikasi
Lean Construction untuk
Meningkatkan Efisiensi
Waktu Pada Proses Produksi
di Industri Precast. Tesis
Program Pascasarjana.
Universitas Indonesia,
Depok.
DOI: http://dx.doi.org/10.32497/wahanats.v26i1.2643
Refbacks
- There are currently no refbacks.
ABOUT JOURNAL
POLICIES | SUBMISSION | PEOPLE |
OFFICE INFORMATION
Publisher : Jurusan Teknik Sipil, Politeknik Negeri Semarang | wahanasipil@polines.ac.id, jurnalwahana@gmail.com https://jurnal.polines.ac.id/index.php/wahana | |||
Department of Civil Engineering, Politeknik Negeri Semarang (State Polytechnic of Semarang) Jl. Prof. Sudarto, SH, Tembalang, Semarang, Indonesia 50275 | +62 24 7473417 Ext. 212 For Journal Subscription |