EVALUASI KINERJA BIAYA DAN WAKTU PELAKSANAAN MENGGUNAKAN METODE EARNED VALUE (EVM) (Studi Kasus: Proyek Pengendalian Banjir Kali Lamong)
Abstract
The Kali Lamong Project is scheduled to be completed within 35 weeks with a
contract value of Rp. 72,000,000,000,-. The purpose of this study is to determine
cost and time performance, cost and time estimates at the end of project completion
and the factors that cause delays or project progress. The method used in this study
is the Earned Value method which combines the elements of cost and time as well as
the physical performance of the work The data obtained from the project includes
the project time schedule, budget plan (RAB), project weekly reports and actual
costs, then an analysis of costs, schedules, variances and performance indexes is
carried out by explaining the problems that arise during the research. From the
results of the analysis it is known that the costs incurred are lower than the
budgeted costs indicated by the value of CPI = 1.12 and the implementation time is
slower than the planned schedule indicated by the value of SPI = 0.71. The results
of the calculation of the estimated final project cost of Rp. 67,952,500,564.98 with
an estimated completion time of 43 weeks, indicating that the project experienced a
delay of 8 weeks from the planned 35 weeks. This delay was caused by various
factors such as delays in the initial erection of the project by a third party, damage
to equipment, changes to the drawings by the planning consultant and changes to
the design by the owner.
Keywords
Full Text:
PDFReferences
D., 1995, Manajemen Konstruksi Profesional. Jakarta Erlangga.
Cleland, D., 1995, Project Management Strategic Design and Implementation. Singapore: MC. Graw Hill, Inc.
Dumadi, T.A., Sunarjono, S., & Sahid, M.N., 2014, Evaluasi Pelaksanaan Proyek Menggunakan Metode Earned
Value Analysis. Simposium Nasional RAPI XIII.
Gardjito, E., 2017, Pengendalian Jadwal Dan Anggaran Terpadu Dengan Metode Earned Value Analysis Pada Pekerjaan Konstruksi. UkaRsT Vol. 1, No.1.
Garza, G.E., & Hernandez, I.L., 2017, Proposed Model to Improve The
Forecast of The Planned Value in The Estimation of The Final Cost of The Construction Project. Procedia Manufacturing.
Iwawo, E.R., J.T., & Pratasis, P.A., 2016, Penerapan Metode CPM
pada Proyek Konstruksi (Studi Kasus Pembangunan Gedung
Baru Kompleks Eben Haezar Manado). Jurnal Sipil Statik Vol. 4, No. 9.
Izeul, M., & Indryani, R., 2015, Metode Earned Value untuk
Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya. Jurnal Teknik ITS Vol. 4 No. 1.
Jay, H., & Barry, R., 2017, Manajemen Operasi. Salemba Empat.
Kartikasari, 2014, Pengendalian Biaya dan Waktu dengan Metode Earned Value (Studi Kasus: Proyek Struktur dan Arsitektur
Production Hall-02 Pandaan). Jurnal Teknik Sipil Untag Surabaya.
Mahardika, D.C., Soeharto, & A.A., 2021, Evaluasi Kinerja Biaya
dan Waktu pada Pelaksanaan Proyek Konstruksi dengan Metode Nilai Hasil. TERAS Vol 11, No. 1.
Maromi, M.I., & Indryani, R., 2015, Metode Earned Value untuk
Analisa Kinerja Biaya dan Waktu Pelasanaan pada Proyek Pembangunan Condotel De Vasa Surabaya. Jurnal Teknik Sipil ITS Vol. 4, No.1.
Messah, Y.A., Lona, L.H., & Sina, D.A., 2013, Pengendalian Waktu
dan Biaya Pekerjaan Konstruksi Sebagai Dampak dari Perubahan
Desain. Jurnal Teknik Sipil Vol. II No. 2.
Mishakova, A., Vakhruskina, A.,
Murgul, V., & Sazonova, T., 2016, Project Control Based on
A Mutual Application of Pertans Earned Value Management
Methods. Procedia Engineering Volume 165.
Muntiyono, A.S., 2020, Evaluasi Pengendalian Biaya dan Waktu
Pelaksanaan Proyek dengan menggunakan Metode Nilai Hasil. Isu Teknologi STT Mandala Vol. 15 No. 1, 13. Rantung, A.H., Sompie, B.F., & Mandagi, R.J., 2014, Analisis Pengendalian Biaya dan Jadwal
pada Tahap Pelaksanaan Konstruksi dengan "Analisis Nilai Hasil" (Earned Value). Jurnal Ilmiah Media Engineering Vol. 4 No. 3.
Soeharto, I., 1995, Manajemen Proyek dari Konseptual Hingga Operational. Jakarta: Erlangga.
Sudarsana, D.K., 2008, Pengendalian Biaya dan Jadual Terpadu pada Proyek Konstruksi. Jurnal Ilmiah Teknik Sipil Vol. 12, No.2. Tarore, H., Malingkas, G.Y., &
Walangitan, D., 2012, Pengendalian Waktu dan Biaya Pada Tahap Pelaksanaan Proyek dengan Menggunakan Metode Nilai Hasil. Jurnal Sipil Statik Vol. 1 No.1.
Wahyuni, E., & Hendrawan, B., 2018, Analisis Kinerja Proyek "Y" Menggunakan Metode Earned Value Management. Journal of Applied Business Administration Vol.2, No.2.
Widiasantri, I., & Lenggogeni, 2013, Manajemen Proyek. Bandung:
Remaja Rosdakarya.
Zhong, S., & Wang, X., (2011, Improvement and application of earned value analysis in coal project manajement. Procedia Engineering 26.
DOI: http://dx.doi.org/10.32497/wahanats.v29i2.6160
Refbacks
- There are currently no refbacks.
ABOUT JOURNAL
POLICIES | SUBMISSION | PEOPLE |
OFFICE INFORMATION
Publisher : Jurusan Teknik Sipil, Politeknik Negeri Semarang | wahanasipil@polines.ac.id, jurnalwahana@gmail.com https://jurnal.polines.ac.id/index.php/wahana | |||
Department of Civil Engineering, Politeknik Negeri Semarang (State Polytechnic of Semarang) Jl. Prof. Sudarto, SH, Tembalang, Semarang, Indonesia 50275 | +62 24 7473417 Ext. 212 For Journal Subscription |