ANALISIS FAKTOR-FAKTOR YANG BERPENGARUH TERHADAP PENURUNAN RISIKO KECELAKAAN KERJA
DOI:
https://doi.org/10.32497/wahanats.v28i2.5242Keywords:
Implementation of SOP, tower crane, risk of work accidentAbstract
The construction process of the AKASA Serpong apartment building requires heavy equipment in the form of a tower crane to facilitate the construction work process, but in its implementation, there are still errors that cause work accidents. Factors causing work accidents such as human skills, geographical conditions, and crane instrumentation are the root of the problem, where the application of SOPs is not implemented properly and correctly. The purpose of the study was to analyze and identify the dominant factors that cause and minimize the risk of work accidents using quantitative descriptive methods conducted through interviews, perceptions of respondents, and questionnaire surveys of 60 workers at the research location, the results were analyzed using the SPSS version 24 program. The results showed that the crane instrumentation factor was more dominant, having a significance value of 0.000 <0.05. As for the t count, the value is 8.235> t table (2.003) so it is very influential on the performance measurement variable of the application of SOPs that are useful for reducing the risk of work accidents.
References
Affiq, M., Ramalan, H., & Hasmori, M.F., 2021, A Study on Human Factor That Lead to Tower Crane Accident at Construction Site in Malaysia. Recent Trends in Civil Engineering and Built Environment, 2(1), 852”“861.
Aprizaldi, M.F., & Saputro, C.D., 2022, Analisis Risiko Kecelakaan Kerja dalam Penggunaan Tower Crane dengan Metode Analitycal Hierarchy Process (AHP) (Studi Kasus Proyek Pembangunan Gedung Teaching Industry Learning Center (TILC) Sekolah Vokasi UGM). Inersia, 18(1), 83”“93.
Bamfo-Agyei, E., & Atepor, L., 2018, Assessing the safety use of tower cranes on construction sites in central region of Ghana. Advances in Intelligent Systems and Computing, 604(July), 486”“496.
Dau, E., Balan, A., & Hasmori, M.F., 2022, A Study of Tower Crane Accidents and its Mitigation Measures. Recent Trends in Civil Engineering and Built Environment, 3(1), 1484”“1491.
Deva, B., Nopiyanti, E., & Susanto, A.J., 2018, Analisis Risiko Pengoperasian Tower Crane Pada Pekerjaan Bekisting Dan Cor Semen Di Proyek Apartemen Enveciio Margonda, Depok. Jukmas, 2(2), 175”“186.
Firmansyah, F., Sidi, P., & Amrullah, H.N., 2018, HIRARC pada Proses Erection Tower Crane di Perusahaan Konstruksi Proyek Pembangunan Apartemen dan Mall. Proceeding 2nd Conference On Safety Engineering, 2581, 723”“728.
Ghozali, I., 2018, Aplikasi Analisis Multivariate dengan Program IBM SPSS 25. Badan Penerbit Universitas Diponegoro: Semarang.
Hamdani, F., & Sucita, I.K., 2022, Optimasi Tata Letak Tower Crane pada Proyek X. MoDuluS: Media Komunikasi Dunia Ilmu Sipil, 4(1), 35-39.
Jamato, H., Aswanto, M., & Trijeti, 2015, Perbandingan penggunaan tower crane dengan mobil crane ditinjau dari efisiensi waktu dan biaya sebagai alat angkat utama pada pembangunan gedung. Seminar Nasional Sains Dan Teknologi, November, 1”“10.
Janna, N.M., & Herianto, 2021, Artikel Statistik yang Benar. Jurnal Darul Dakwah Wal-Irsyad (DDI), 18210047, 1”“12.
Jiang, T., 2020, Safety Risk Analysis and Control of Tower Crane. IOP Conference Series: Earth and Environmental Science, 546(4).
Lestari, A.D., Herzanita, A., & Latief, Y., 2021, Development of Safety Plan Building Based on Work Breakdown Structure (WBS) in Campus Area of UI Depok to Reduce Work Accident. Journal of International Conference Proceedings, 4(1), 104”“116.
Pangestu, R.A., Utoyo, S., & Lydianingtias, D., 2021, Analisis Penggunaan Tower Crane Untuk Pekerjaan Struktur Pada Proyek One Signature Gallery Surabaya. Jurnal JOS-MRK, 2(2), 27”“34.
Rahim Abdul Hamid, A., Azhari, R., Zakaria, R., Aminudin, E., Putra Jaya, R., Nagarajan, L., Yahya, K., Haron, Z., & Yunus, R., 2019, Causes of crane accidents at construction sites in Malaysia. IOP Conference Series: Earth and Environmental Science, 220(1).
Salihu, A.A., Aliyu, S.S., & Abubakar, M., 2021, An evaluation of safety risk factors during installation and dismantling of tower cranes in construction sites. Nigerian Journal of Technology, 39(4), 992”“1000.
Soekiswara, T.E.F., 2020, Faktor Kecelakaan Dan Keselamatan Kerja Pada Penggunaan Crane Di Proyek Konstruksi. Jurnal Menara, 18(2), 42”“50.
Soltanmohammadlou, N., Sadeghi, S., & Hon, C.K.H., 2019, Real time locating systems and safety in construction sites: a literature review. Safety Science, 117, 229”“242.
Zhou, W., Zhao, T., Liu, W., & Tang, J., 2018, Tower crane safety on construction sites: A complex sociotechnical system perspective”™, Safety Science. Elsevier, 109(Nov 2018), 95”“108.
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).