FAKTOR PENYEBAB KETERLAMBATAN PROYEK PEMBANGUNAN MASJID 99 KUBAH CENTER POINT OF INDONESIA MAKASS

Genio Geofany Sidabutar, Josefine Ernestine Latupeirissa, Meti Meti

Abstract


The construction of the 99 Dome Asmaul Husna Mosque Center Point of Indonesia Makassar has been delayed. Therefore the purpose of this study is to analyze the factors causing the delay in the construction of the mosque. The method of data collection was in the form of direct observation on the project and distributing questionnaires to those involved in the project, totaling 20 respondents. Test the validity and reliability of the 54 sub-factors of delay obtained from the results of literature review and observations in the field, categorized into 10 factors. Data analysis using RRI obtained 10 top ranking subfactors from seven factors. The conclusion based on the results of the research is that the sub-factors that cause delays in the implementation of the project sequentially are, the unexpected events of the COVID'19 pandemic, the RRI value = 0.892, the ability of the foreman or operator who is lacking in operating equipment, the RRI value = 0.800, the intensity of rainfall, the RRI value = 0.775, the workforce discipline, the RRI value = 0.767, the planned work order that is not well structured/integrated RRI value = 0.750, work space requirements RRI value = 0.750, payment difficulties by the owner RRI value = 0.742, access to the project location RRI value = 0.717, the work that has been completed must be corrected due to an error in processing the RRI value = 0.667, as well as the process of checking and evaluating the progress of work past the agreed schedule RRI value = 0.658

Keywords


delay in project implementation, delay factor, Relative Rank Index

Full Text:

PDF

References


Assaf, S. A., Al-Hejji, S, 2006.,Causes of delay in large construction projects in Saudi Arabia. Internasional Journal of Project Management, 24(4), 349-357

Basyiroh, N.N., Moehammad, & Nugraha, A, 2018, Analisis Persebaran dan Kebutuhan Tempat Ibadah Berdasarkan Jumlah Penduduk Berbasis Sig (Studi Kasus: 4 Kelurahan di Kecamatan Banyumanik) Jurnal Geodesi Undip Oktober 2018 Jurnal Geodesi UNDIP, 7 (4), 27-36

Cooper, D. R, & Schindler, P. S. 2014, Bussiness Research Methods. 12th. Twelfth Edition. New York: Mc Graw Hill

Ghozali, I. 2012, Aplikasi Analisis Multivariate dengan Program IBM SPSS 20, Semarang. UNDIP

González, P., González, V., Molenaar, K & Orozco, F., 2014, Analysis of Causes of Delay and Time Performance in Construction Projects. Journal of Construction Engineering and Management, 140(1), 04013027

Harpe, S.E, 2015, Review article : How to analyze Likert and other rating scale data, Currents in Pharmacy Teaching and Learning 7. Elsevier Inc.. pp 836–850

iNews Sulsel, 2020, Pengerjaan Masjid 99 Kubah Terhambat Lagi karena Pekerja Terpapar Covid. http://sulsel.inews.id/ 18 Agustus 2020. Akses Desember 2021 iNew Sulsel, 2021, Pembangunan Masjid Kubah 99 Terlambat

Mangitung, D.M., 2006, Faktor-Faktor yang Penting dalam Sistem Penilaian Kompetensi Kontraktor Berdasarkan Persepsi Kontraktor di Kota Palu. Majalah Ilmiah MEKTEK Tahun VIII No. 1 Januari 2006 Munsir, I., 2022, Mulai Berfungsi Hari Ini, Berikut 8 Fakta Masjid 99 Kubah

Peraturan Menteri, 2006, Peraturan Bersama Menteri Agama Nomor: 9 Tahun 2006 Dan Menteri Dalam Negeri Nomor : 8 Tahun 2006. Tentang Pedoman Pelaksanaan Tugas Kepala Daerah/Wakil Kepala Daerah Dalam Pemeliharaan Kerukunan Umat Beragama, Pemberdayaan Forum Kerukunan Umat Beragama, Dan Pendirian Rumah Republika, 2021, Target Pembangunan Masjid 99 Kubah Alami Keterlambatan https://www.republika.co.id › 12 Juli 2021. Akses Desember 2021

Sambasivan, M. & Soon, Y.W., 2007. Causes and Effects of Delays in Malaysian Construction Industry. International Journal of Project Management, 25(5):517-526

Sugiyono, S., 2015, SPSS20 Pengolah Data Statistik DI Era Informasi. PT Elax Media Komputindo. Jakarta World Population Review, 2020, Populasi Muslim di Indonesia adalah yang terbanyak di dunia




DOI: http://dx.doi.org/10.32497/wahanats.v28i1.4561

Refbacks

  • There are currently no refbacks.


ABOUT JOURNAL

 POLICIES

SUBMISSION

 PEOPLE


OFFICE INFORMATION

 Publisher : Jurusan Teknik Sipil, Politeknik Negeri Semarang  wahanasipil@polines.ac.id, jurnalwahana@gmail.com https://jurnal.polines.ac.id/index.php/wahana
 Department of Civil Engineering, Politeknik Negeri Semarang (State Polytechnic of Semarang) Jl. Prof. Sudarto, SH, Tembalang, Semarang, Indonesia 50275  +62 24 7473417 Ext. 212 For Journal Subscription

Creative Commons License
Wahana TEKNIK SIPIL: Jurnal Pengembangan Teknik Sipil (p-ISSN : 0853-8727 | e-ISSN : 2527-4333) is published by Politeknik Negeri Semarang under Creative Commons Attribution 4.0 International License.