PENGAPLIKASIAN MSPAS DI MSPROJECT PADA PROYEK PEMBANGUNAN GEDUNG KULIAH DAN LABORATORIUM POLITEKNIK PARIWISATA LOMBOK

PENGAPLIKASIAN MSPAS DI MSPROJECT PADA PROYEK PEMBANGUNAN GEDUNG KULIAH DAN LABORATORIUM POLITEKNIK PARIWISATA LOMBOK

Authors

  • Rajabi Mubarak Universitas Muhammadiyah Mataram
  • Hafiz Hamdani Universitas Muhammadiyah Mataram
  • M. yusuf Nur Universitas Muhammadiyah Mataram

DOI:

https://doi.org/10.32497/bangunrekaprima.v11i2.7224

Keywords:

Project Scheduling, MSPAS, Microsoft Project, Project Duration, Critical Path

Abstract

Project scheduling is a crucial component of construction management, serving as a reference for controlling time, resources, and project progress. Selecting an appropriate scheduling method is essential to ensure that project implementation proceeds effectively and efficiently. This study examines the application of the Model Schedule Project ala Syafriandi (MSPAS) method in a construction project using Microsoft Project software. MSPAS consists of three main components—planning, scheduling, and tracking—which collectively provide comprehensive information regarding project duration, activity dependencies, resource performance, and progress evaluation. The results indicate that the use of MSPAS enhances project efficiency by reducing the project duration from 270 days to 256 days, as well as decreasing indirect project costs by IDR 298,453,596. Furthermore, 287 critical activities were identified, including preparatory work, structural work, architectural work, mechanical, electrical, and plumbing tasks. Therefore, MSPAS can be considered an effective method for optimizing project time and cost in construction management.

Author Biographies

Rajabi Mubarak, Universitas Muhammadiyah Mataram

Prodi Teknik Sipil, Universitas Muhammadiyah Mataram

Hafiz Hamdani, Universitas Muhammadiyah Mataram

Prodi Teknik Sipil, Universitas Muhammadiyah Mataram

M. yusuf Nur, Universitas Muhammadiyah Mataram

Prodi Teknik Sipil, Universitas Muhammadiyah Mataram

References

Abdullah, R., Marsudi, S., & Cahya, E. N. (2021). Studi penjadwalan dan pembiayaan proyek Trashlog PLTA Orya Genyem Kecamatan Unurum Guay Kabupaten Jayapura menggunakan Microsoft Project Manager 2016. Jurnal Teknologi Dan Rekayasa Sumber Daya Air, 1(1), 150–157. https://doi.org/10.21776/ub.jtresda.2021.001.01.13

Auliansyah, C. R., Irawan, J. D., & Ariwibisono, F. X. (2022). Rancang bangun sistem monitoring manajemen proyek konstruksi menggunakan kurva-S. Jurnal Teknik ITS, 6(2), 1106–1114.

Hutabarat, E. M., Irena, N., Gaol, L., & Sitompul, M. (2023). Microsoft Project pada proyek pembangunan gedung. Seminar Nasional Terapan Riset Inovatif (SENTRINOV), 9, 986–995.

Imanuel, C., Nangka, G., Sibi, M., & Mangare, J. (2018). Perataan tenaga kerja pada proyek bangunan dengan menggunakan Microsoft Project (Studi kasus: Proyek pembangunan Terminal Akap Tangkoko Bitung). Jurnal Sipil Statik, 6(11), 867–874.

Juansyah, Y., Oktarina, D., & Zulfiqar, M. (2017). Analisis perbandingan rencana anggaran biaya bangunan menggunakan metode SNI dan BOW. Jurnal Muara Sains, Teknologi, Kedokteran Dan Ilmu Kesehatan, 1(1), 27–33. https://doi.org/10.24912/jmstkik.v1i1.429

Ladda, S., Chanda, P., & Khedekar, S. (2017, December). Planning and scheduling of a project using Microsoft Project. International Journal of Advanced Research in Engineering and Technology (IJARET), 8(6), 10–18.

Munandar, M. I., & Rezeki, I. M. (2020). Manajemen konstruksi proyek pembangunan guest house Sutan Raja Kota Cirebon. Jurnal Konstruksi dan Infrastruktur, 6(2), 87–96.

Putri, G. N., & Anif, B. (2019). Pembangunan gedung puskesmas Sungai Tarab II dengan menggunakan aplikasi Microsoft Project. *Jurnal Online Mahasiswa (JOM) FT-UNB, 1*(1).

Saputra, T. A., & Anwar, S. (2020). Analisis manajemen konstruksi pada bendung Copong Kabupaten Garut. Jurnal Konstruksi dan Infrastruktur, 8(2), 47–56.

Siddiq, A. (2022). Analisis penjadwalan menggunakan aplikasi Microsoft Project 2010 (Studi kasus: Ruang terbuka hijau (RTH) Kabupaten Wajo). Jurnal Ilmiah Media Engineering, 2(2), 222–230.

Soedradjat, A. S. (1984). Analisa anggaran biaya pelaksanaan. Bandung: Nova.

Sulistia, D., & Agustina, I. D. (2023). Penjadwalan proyek dengan kurva-S pada pembangunan perumahan di Kota Bekasi. Jurnal Al Ulum LPPM Universitas Al Washliyah Medan, 11(2), 100–106. https://doi.org/10.47662/alulum.v11i2.540

Syafriandi & Luthan, P. L. A. (2017). Manajemen konstruksi dengan aplikasi Microsoft Project. Yogyakarta: Deepublish.

Widiasanti, I., & Lenggogeni. (2013). Manajemen konstruksi. Jakarta: PT. Rekayasa Cendikia